Balongan- Mundu Pipe Line

Project Description

9 Km Length of 12” OD pipe was being coated for Balongan- Mundu project for Pertagas started in 28 November 2014 and finish in 3 December 2014. Another 10 Km for the same project of 3LPE External Coating for which was started in 18 December 2014 and finish in 29 December 2014 in accordance with this 4 Km was being Concrete Weight Coated (CWC).

Project Detail

Customer : Pertagas
Project Name : Balongan - Mundu Project
Project Location : Balongan - Mundu, Indonesia
Total Length : 9 Km
End User : PT. Pertamina Gas
Coating Specification : 3LPE : 2mm thk, CWC : 50mm thk
Year Completed : 2014